管(guan)樁加工(gong)廠為您分享交樁的相關知識,一起看看吧!
施工用(yong)(yong)軸線控(kong)(kong)制(zhi)點(dian)(dian)、水(shui)平控(kong)(kong)制(zhi)點(dian)(dian)一般由政府(fu)勘(kan)(kan)探(tan)、測(ce)繪部門根據規劃、設計部門的要(yao)求(qiu)和計劃,利(li)用(yong)(yong)測(ce)控(kong)(kong)網施放(fang)利(li)于施工的控(kong)(kong)制(zhi)點(dian)(dian),這些(xie)點(dian)(dian)通常是標設在(zai)較為固定的樁(zhuang)上,施工前(qian),勘(kan)(kan)探(tan)、測(ce)繪單位將(jiang)它交(jiao)給施工單位,施工單位在(zai)據以引(yin)測(ce)工程軸線和施工放(fang)線。有時(shi)控(kong)(kong)制(zhi)軸線的樁(zhuang)采用(yong)(yong)龍門樁(zhuang),也稱“角樁(zhuang)”。交(jiao)代軸線控(kong)(kong)制(zhi)點(dian)(dian)、水(shui)平控(kong)(kong)制(zhi)點(dian)(dian)的過程簡稱為“交(jiao)樁(zhuang)”。
1、樁位
要(yao)仔細觀察樁位周圍比較(jiao)特(te)殊的地(di)物、地(di)貌,及和路線(xian)中(zhong)樁的關系,保證能夠隨時(shi)找到(dao)樁位。
2、起點(dian)、終點(dian)樁位
起點(dian)樁位(wei)與終(zhong)點(dian)樁位(wei)的(de)位(wei)置(zhi)和坐標(biao)的(de)確定性(xing)。現在一般為附(fu)和導(dao)線形式(shi),導(dao)線起點(dian)樁位(wei)及終(zhong)點(dian)管樁(zhuang)位(wei)往往不是(shi)的(de)標準(zhun)點,也(ye)有可(ke)能由于外(wai)部條件而發生(sheng)變動,偏移等,另外(wai)也(ye)是(shi)相鄰(lin)標段的(de)起點或終點,所以非常重要,必(bi)須(xu)是(shi)正(zheng)確或正(zheng)確采用的(de)。
3、交樁的(de)資(zi)料
當然是越齊(qi)全(quan)越好,而且(qie)要(yao)有齊(qi)全(quan)的簽字,尤為重要(yao)的是補(bu)充性和變更的文件必須交(jiao)接(jie)齊(qi)全(quan),一般開工前(qian),業(ye)主會叫設(she)計單位下(xia)來進行交(jiao)樁,一般就(jiu)是水(shui)準(zhun)點和控(kong)制點。我們(men)施工單位需要(yao)做交(jiao)樁記錄(lu),并現場簽字。
4、交樁的參(can)加人(ren)員
應該(gai)包括建(jian)設單位、監理單位、施工單位如有需(xu)要還應有設計(ji)單位共同參加并簽字。
5、應(ying)隨時(shi)觀察樁位對施工(gong)的影(ying)響
合適的(de)馬上進行加固(gu),不合適的(de)注意觀察地形,初步了解加樁(zhuang)、或移樁(zhuang)的(de)位(wei)置(zhi),為下布工作打好(hao)基礎(chu)。